top of page

Parsonage Project Update

Updated: Nov 17, 2024

November 17, 2024


Construction News: The framing and walls are all completed. The roofers are nearly done with the roofing and shingle work the new build. Some of the windows are already in – the addition will likely be weather tight sometime this week.


A BIG Thank You to the volunteer crew that showed up again on Saturday to work with the rest of the radiator and pipe removal. Many hands made light(er) the work 😉.


Project Fund Update: as of 11/6/24:


Norseland congregation

total project gifts in-hand: $94,900

Norwegian Grove congregation

total project gifts in-hand: $67,500


*This now includes the $30K draw from legacy monies for use on the project as well.




 

November 10, 2024


Construction News:

  • The framework is nearing completion as the roofline of the addition is being tied into the existing roofline.

  • These days, when the weather is amiable, LOTS of visible progress is being made.

Project Fund Update:

Project Fund Updates as of 11/6/24:


NS total project gifts in-hand:          $94,900

NG total project gifts in-hand:          $37,500

Total $132,400


*Nor' Grove will have a $30K draw from legacy monies next week for use on the project as well.

We have been keeping up with the bills so far but anticipate more larger bills coming soon. Our total expenses to date have been $90,552.86. Contributions from both churches have allowed us to pay all bills so far.

~ Steve Molnau



 

October 27, 2024


Construction News:

  • This past week, radiators and old hot-water heat piping continued to be removed. This labor was intense! A big "Thank You" to John Merseth II and III as well as Gabe and Nathan Merseth for the very heavy lifting.

  • The backfilling of the new basement walls happened on Wednesday.

  • The trusses for the new build were delivered at the beginning of the week.

  • We had a VERY productive volunteer day on Saturday, October 26 with 3 generations of men helping with the work. All the siding was removed from the west side of the house.


Project Fund Update:

 

NS total project gifts in-hand:          $84,900

NG total project gifts in-hand:          $37,500

Total $122,400





 

October 20, 2024


Construction News:

  • Tuesday, October 15th, the concrete foundation and block work was tarred and then covered with insultation panels and plastic. It is now ready for backfill.

  • Thursday and Friday, the heating, ventilation, and air conditioning crew was busy setting up the new system. The new HVAC system should be operational during the week of October 21.


Project Fund Update:

 

NS total project gifts in-hand:          $82,900

($25,500 from 10/6 offerings)

NG total project gifts in-hand:          $37,500

Total $120,400

  • $5,000 more is expected before 10/31.


Note: The gorgeous fall colors in the Norseland Cemetery were begging to be photographed this morning.


 

October 10, 2024


Construction News:

  • Thanks to many helping hands, the new basement door has been cut, a new sump has been placed, nearly all of the block has been laid for the new addition basement, and the exterior limestone wall of the existing basement has been pressure washed for sealant application. The concrete floor was set to be poured on Friday.  Lots of work is getting done every day.


Project Fund Update:

 

NS total project gifts in-hand:          $71,400

($25,500 from 10/6 offerings)

NG total project gifts in-hand:          $34,500

Total $105,900




 

October 6, 2024


Construction News:

  • The foundation hole has been dug and concrete block is sitting in the excavated area ready to be installed. A door has been fitted from the old basement to what will be the extended basement space.

  • The boiler has been drained and work on the furnace should take place starting the week of October 7th. Cement block work on the foundation will also start this week and be ongoing.

  • John Merseth sent out a call for volunteers to help Saturday, October 5th. Both old and young men arrived starting at 9 am to do some heavy lifting. Tasks included removing stone for the doorway, helping remove pipes, etc. out of the basement and installing a sump basket.



Financial Updates: the most current information available is as follows:

  • Norseland Parsonage Contributions as of 10/2:   ~ $45,563 $11,200 contributed on 9/29/2024

  • Norwegian Grove Parsonage Contributions as of 10/2:   ~ $35K

  • Checks to pay bills for materials ordered went out last week --> $87,500

 

September 28, 2024


The following link has photos of the project that will be updated regularly by the Norseland Parish. Norseland will continue to add progress pictures week-by-week.


Construction Weekly Progress:

1.)    Monday, the excavators dug the hole for the basement (and a bit of tiling as well).

2.)    Friday the concrete footings were poured, and tiling was put into place. Some more drainage work will take place before blocks begin to be laid.


Financial Updates: the most current information available is as follows:

  • Norseland Parsonage Contributions as of 9/26:   ~ $34.5K

  • Norwegian Grove Parsonage Contributions as of 9/26:   ~ $35K

  • Checks to pay bills for materials ordered went out this week --> $87,500


With contracted work underway now, the invoices for labor and materials will be coming in at a steady pace until job completion. Thanks to all for your generous contributions already made AND that forthcoming soon. 

Steve Molnau & Ben Tollefson


 

September 22, 2024


Construction News: The general contractor for the project is Unique Designs – owned and operated by John & Jeremy Merseth.

 

Groundbreaking Ceremony: 10am September 22, 2024

We will acknowledge and initiate this major parish project and ask the Lord's blessings upon it. Here are some photos of the groundbreaking ceremony and the current progress of work.




 

Oak Lumber Available (cut and haul yourself):   

Prior to the construction, some preparations involved clearing trees around the construction area. Consequently, there are some robust oak logs (requiring sawing) ready for use in the southwestern tree boundary of the parsonage premises. Feel free to take them if needed!

 

Financial Updates:

  • NS Parsonage Contributions as of 9/21:  ~ $32K 

  • NG Parsonage Contributions as of 9/21:  ~ $35K


Project expenses will come due quite quickly now as contractors will be incurring material and labor expenses in a short amount of time (Lord willing).  So, there's no time like the present to thoughtfully consider how you and your household might be able and willing to support in this way. 

Steve Molnau & Ben Tollefson

 

Volunteer Opportunities:  More opportunities will be forthcoming for eager and willing hands.  Thanks much!

                                ~ Rod Tollefson & Eric Annexstad


More Photos:




62 views

Recent Posts

See All

Komentarze


bottom of page